110 tasks · 11 phases

Programme Gantt chart

W0 – W29 schedule across ground network, RAN, core, aircraft certification, logistics, installation, PSM and customer experience — taken from the POC project timeline sheet.

The MS Project file opens directly in Microsoft Project, where you can save it as .mpp. Upload an Excel file with the POC timeline sheet (WBS number, task title, owner, start and due week, % complete) to refresh the chart — it is saved for every visit until you reset it.

Programme progress

W0 of W29 · 29 weeks to GO phase

0%
of W29
W0 KickoffW1 ContractW15 MidpointW29 Finish
Programme progress
0%
Current week
W0
Weeks remaining
29
Milestones done / active
17 / 4

Phase flow

  1. 01W0 – W3

    GN: Initial Phase

    4 tasks in the active Gantt plan.

    Ongoing
  2. 02W0 – W9

    RAN Design Phase

    14 tasks in the active Gantt plan.

    Ongoing
  3. 03W4 – W21

    RAN Material Shipment and Logistics

    4 tasks in the active Gantt plan.

    Planned
  4. 04W4 – W24

    RAN Integration Phase

    12 tasks in the active Gantt plan.

    Planned
  5. 05W4 – W21

    Core Preparation Phase

    10 tasks in the active Gantt plan.

    Planned
  6. 06W0 – W7

    Aircraft: Initial Phase

    5 tasks in the active Gantt plan.

    Ongoing
  7. 07W6 – W20

    Preparation Phase (Certificates Required)

    12 tasks in the active Gantt plan.

    Planned
  8. 08W0 – W18

    Material and Logistics Phase

    28 tasks in the active Gantt plan.

    Ongoing
  9. 09W4 – W24

    Installation and Integration Phase

    13 tasks in the active Gantt plan.

    Planned
  10. 10W0 – W10

    PSM (Passenger Software Manager) Phase

    4 tasks in the active Gantt plan.

    Ongoing
  11. 11W23 – W29

    Customer Experience Phase

    4 tasks in the active Gantt plan.

    Planned
Task / owner
GN: Initial Phase
RAN Design Phase
RAN Material Shipment and Logistics
RAN Integration Phase
Core Preparation Phase
Aircraft: Initial Phase
Preparation Phase (Certificates Required)
Material and Logistics Phase
Installation and Integration Phase
PSM (Passenger Software Manager) Phase
Customer Experience Phase
W0
W1
W2
W3
W4
W5
W6
W7
W8
W9
W10
W11
W12
W13
W14
W15
W16
W17
W18
W19
W20
W21
W22
W23
W24
W25
W26
W27
W28
W29
GN: Initial Phase
RAN Design Phase
RAN Material Shipment and Logistics
RAN Integration Phase
Core Preparation Phase
Aircraft: Initial Phase
Preparation Phase (Certificates Required)
Material and Logistics Phase
Installation and Integration Phase
PSM (Passenger Software Manager) Phase
Customer Experience Phase