30 tasks · 9 milestones

Programme Gantt chart

26-week schedule from kickoff (W0) and contract signature (W1) to the GO phase, with the 6-week modified installation kit and the ground network as the remaining critical path.

The MS Project file opens directly in Microsoft Project, where you can save it as .mpp.

Programme progress

W0 of W26 · 26 weeks to GO phase

0%
of W26
W0 KickoffW1 ContractW16 InstalledW24 FlyW26 GO
Programme progress
0%
Current week
W0
Weeks remaining
26
Milestones done / active
0 / 0

Phase flow

  1. 01W0 – W2

    Mobilise

    Kickoff, contract signature, spectrum, site planning and POs.

    Planned
  2. 02W2 – W11

    CORE Network

    CORE design (2w) then CORE implementation (7w).

    Planned
  3. 03W2 – W12

    POC Portal (IT)

    Phase 1 portal feature set and airline integration.

    Planned
  4. 04W4 – W12

    Regulatory & MRO

    SB submission, MRO agreement signed, STC approval.

    Planned
  5. 05W8 – W12

    Aircraft Hardware

    Modified Eclipse kit (6w), Thales OBE, Kontron CS/WAP.

    Planned
  6. 06W13 – W16

    Logistics & Install

    Shipment, customs release, MRO installation.

    Planned
  7. 07W18 – W23

    Ground Network

    Critical path: hardware, customs, 10 sites in 3w, implementation.

    Planned
  8. 08W24 – W26

    GO Phase

    POC flights, performance data, GO phase.

    Planned
Task / owner
Mobilisation
Kickoff meeting
POC contract signed
Spectrum, planning and POs
Aircraft survey
CORE Network
CORE design (2w)
CORE implementation (7w)
POC Portal (IT)
Portal build — full Phase 1 features
Airline integration (current A2G airline)
Portal testing and go-live readiness
Regulatory & MRO
SB submitted to CAA
MRO agreement negotiation (4w)
MRO agreement signed
CAA review
STC approval
Aircraft Hardware
Installation kit — existing kit modified (6w)
Installation kit ready
OBE production (8w)
CS & WAP production (10w)
All aircraft hardware ready
Logistics & Installation
Shipment and logistics (2w)
Customs release (1w)
Aircraft installation (1w)
Aircraft waiting for ground network
Ground Network
GN hardware production (16w)
GN customs release
10 GN sites installed (3w)
GN implementation and CORE integration (1w)
GO Phase
POC test flights
Performance data collection
GO phase and contracts
W0
W1
W2
W3
W4
W5
W6
W7
W8
W9
W10
W11
W12
W13
W14
W15
W16
W17
W18
W19
W20
W21
W22
W23
W24
W25
W26
Mobilisation
W2–W2
W2–W4
CORE Network
W2–W4
W4–W11
POC Portal (IT)
W2–W9
W6–W11
W10–W12
Regulatory & MRO
W2–W6
W4–W12
Aircraft Hardware
W2–W8
W2–W10
W2–W12
Logistics & Installation
W13–W15
W15–W16
W16–W17
W17–W23
Ground Network
W2–W18
W18–W19
W19–W22
W22–W23
GO Phase
W24–W25