110 tasks · 11 phases
Programme Gantt chart
W0 – W29 schedule across ground network, RAN, core, aircraft certification, logistics, installation, PSM and customer experience — taken from the POC project timeline sheet.
The MS Project file opens directly in Microsoft Project, where you can save it as .mpp. Upload an Excel file with the POC timeline sheet (WBS number, task title, owner, start and due week, % complete) to refresh the chart — it is saved for every visit until you reset it.
Programme progress
W0 of W29 · 29 weeks to GO phase
- Programme progress
- 0%
- Current week
- W0
- Weeks remaining
- 29
- Milestones done / active
- 17 / 4
Phase flow
- 01W0 – W3
GN: Initial Phase
4 tasks in the active Gantt plan.
Ongoing - 02W0 – W9
RAN Design Phase
14 tasks in the active Gantt plan.
Ongoing - 03W4 – W21
RAN Material Shipment and Logistics
4 tasks in the active Gantt plan.
Planned - 04W4 – W24
RAN Integration Phase
12 tasks in the active Gantt plan.
Planned - 05W4 – W21
Core Preparation Phase
10 tasks in the active Gantt plan.
Planned - 06W0 – W7
Aircraft: Initial Phase
5 tasks in the active Gantt plan.
Ongoing - 07W6 – W20
Preparation Phase (Certificates Required)
12 tasks in the active Gantt plan.
Planned - 08W0 – W18
Material and Logistics Phase
28 tasks in the active Gantt plan.
Ongoing - 09W4 – W24
Installation and Integration Phase
13 tasks in the active Gantt plan.
Planned - 10W0 – W10
PSM (Passenger Software Manager) Phase
4 tasks in the active Gantt plan.
Ongoing - 11W23 – W29
Customer Experience Phase
4 tasks in the active Gantt plan.
Planned