30 tasks · 9 milestones
Programme Gantt chart
26-week schedule from kickoff (W0) and contract signature (W1) to the GO phase, with the 6-week modified installation kit and the ground network as the remaining critical path.
The MS Project file opens directly in Microsoft Project, where you can save it as .mpp.
Programme progress
W0 of W26 · 26 weeks to GO phase
- Programme progress
- 0%
- Current week
- W0
- Weeks remaining
- 26
- Milestones done / active
- 0 / 0
Phase flow
- 01W0 – W2
Mobilise
Kickoff, contract signature, spectrum, site planning and POs.
Planned - 02W2 – W11
CORE Network
CORE design (2w) then CORE implementation (7w).
Planned - 03W2 – W12
POC Portal (IT)
Phase 1 portal feature set and airline integration.
Planned - 04W4 – W12
Regulatory & MRO
SB submission, MRO agreement signed, STC approval.
Planned - 05W8 – W12
Aircraft Hardware
Modified Eclipse kit (6w), Thales OBE, Kontron CS/WAP.
Planned - 06W13 – W16
Logistics & Install
Shipment, customs release, MRO installation.
Planned - 07W18 – W23
Ground Network
Critical path: hardware, customs, 10 sites in 3w, implementation.
Planned - 08W24 – W26
GO Phase
POC flights, performance data, GO phase.
Planned