Proof of Concept · Oman · Omantel · Salam Air

In-flight Connectivity
POC Deployment

32-week milestone plan from kickoff to GO phase — spectrum, CORE network, regulatory approval, hardware lead times, ground network rollout and test flights.

  • Start / End
  • Process
  • Decision gate
  • Input / Output
  • Wait state

Programme progress

W0 of W26 · 26 weeks to GO phase

0%
of W26
W0 KickoffW1 ContractW16 InstalledW24 FlyW26 GO
Programme progress
0%
Current week
W0
Weeks remaining
26
Milestones done / active
0 / 0

Phase flow

  1. 01W0 – W2

    Mobilise

    Kickoff, contract signature, spectrum, site planning and POs.

    Planned
  2. 02W2 – W11

    CORE Network

    CORE design (2w) then CORE implementation (7w).

    Planned
  3. 03W2 – W12

    POC Portal (IT)

    Phase 1 portal feature set and airline integration.

    Planned
  4. 04W4 – W12

    Regulatory & MRO

    SB submission, MRO agreement signed, STC approval.

    Planned
  5. 05W8 – W12

    Aircraft Hardware

    Modified Eclipse kit (6w), Thales OBE, Kontron CS/WAP.

    Planned
  6. 06W13 – W16

    Logistics & Install

    Shipment, customs release, MRO installation.

    Planned
  7. 07W18 – W23

    Ground Network

    Critical path: hardware, customs, 10 sites in 3w, implementation.

    Planned
  8. 08W24 – W26

    GO Phase

    POC flights, performance data, GO phase.

    Planned

Milestone timeline

Tap any week to open its tasks — click a status badge to cycle Planned → Ongoing → Completed. Your changes are saved in this browser.

  1. W16 – W23

    Aircraft Waiting for Ground Network

    Process

    Installed aircraft waits for the ground network to go live.

    • ProgrammeAircraft installed, awaiting GN readiness.
    • Omantel · NokiaGround network delivery drives the flight date.

    With the 6-week kit lead, the aircraft is ready well before the ground network; this wait is the remaining schedule float.