Proof of Concept · Oman · Omantel · Salam Air

In-flight Connectivity
POC Deployment

W0–W29 live plan from the active Gantt schedule — including uploaded and edited tasks, owners, timing and status updates.

  • Start / End
  • Process
  • Decision gate
  • Input / Output
  • Wait state

Programme progress

W0 of W29 · 29 weeks to GO phase

0%
of W29
W0 KickoffW1 ContractW15 MidpointW29 Finish
Programme progress
0%
Current week
W0
Weeks remaining
29
Milestones done / active
17 / 4

Phase flow

  1. 01W0 – W3

    GN: Initial Phase

    4 tasks in the active Gantt plan.

    Ongoing
  2. 02W0 – W9

    RAN Design Phase

    14 tasks in the active Gantt plan.

    Ongoing
  3. 03W4 – W21

    RAN Material Shipment and Logistics

    4 tasks in the active Gantt plan.

    Planned
  4. 04W4 – W24

    RAN Integration Phase

    12 tasks in the active Gantt plan.

    Planned
  5. 05W4 – W21

    Core Preparation Phase

    10 tasks in the active Gantt plan.

    Planned
  6. 06W0 – W7

    Aircraft: Initial Phase

    5 tasks in the active Gantt plan.

    Ongoing
  7. 07W6 – W20

    Preparation Phase (Certificates Required)

    12 tasks in the active Gantt plan.

    Planned
  8. 08W0 – W18

    Material and Logistics Phase

    28 tasks in the active Gantt plan.

    Ongoing
  9. 09W4 – W24

    Installation and Integration Phase

    13 tasks in the active Gantt plan.

    Planned
  10. 10W0 – W10

    PSM (Passenger Software Manager) Phase

    4 tasks in the active Gantt plan.

    Ongoing
  11. 11W23 – W29

    Customer Experience Phase

    4 tasks in the active Gantt plan.

    Planned

Milestone timeline

Every Gantt task appears here live. Open a card for details or click its status to update every page and export.

  1. W0 – W1

    allocate available Flynas installation kit

    Process

    Material and Logistics Phase · SKYFive

    • SKYFiveallocate available Flynas installation kit
    Hide details
  2. W0 – W1

    allocate cabin server and CWAP (Kontron)

    Process

    Material and Logistics Phase · SKYFive

    • SKYFiveallocate cabin server and CWAP (Kontron)
    Hide details
  3. W1 – W3

    POC contract signature

    Process

    GN: Initial Phase · SKYFive | Oman Tel | Salam Air

    • SKYFive | Oman Tel | Salam AirPOC contract signature
    Hide details
  4. W4 – W5

    allocate OBE with AG for POC

    Process

    Material and Logistics Phase · SKYFive

    • SKYFiveallocate OBE with AG for POC
    Hide details