Kickoff
All POC partners align and launch the programme.
Page 2 · Executive view
Omantel and Salam Air paths converge into aircraft installation, POC flights and the GO Phase.
All POC partners align and launch the programme.
Contract signed after kickoff alignment — the plan starts here.
Spectrum, planning, POs and MRO activity begin.
Omantel completes network design in 2 weeks.
Seven-week implementation programme.
IT builds the portal with all Phase 1 features for the current A2G airline.
Eclipse submits the SB for STC approval.
Salam Air signs the MRO agreement.
Regulatory approval gate is cleared.
Existing installation kit modified — 6-week lead only.
Thales aircraft hardware is ready.
Kontron CS/WAP completes the aircraft set.
Nokia ground hardware — now the critical path.
Shipment, release and transfer to MRO.
One-week installation at the MRO.
Installed aircraft waits for ground coverage to go live.
Ten ground sites installed in three weeks.
Ground network integrated with the CORE.
Test flights from Salalah → Muscat or Muscat → Riyadh.
Collect and evaluate in-flight results.
Programme moves into the GO phase and contracts.