Back to full timeline

Page 2 · Executive view

Main milestone flow chart

Omantel and Salam Air paths converge into aircraft installation, POC flights and the GO Phase.

W0 · 0%
W0

Kickoff

All POC partners align and launch the programme.

W1

POC Contract Signed

Contract signed after kickoff alignment — the plan starts here.

W2

Parallel Work Starts

Spectrum, planning, POs and MRO activity begin.

CORE & Portal
W2–W4

CORE Design

Omantel completes network design in 2 weeks.

W4–W11

CORE Implementation

Seven-week implementation programme.

W2–W12

POC Portal (IT)

IT builds the portal with all Phase 1 features for the current A2G airline.

Approval Path
W4

CAA Submission

Eclipse submits the SB for STC approval.

W6

MRO Agreement

Salam Air signs the MRO agreement.

W12

STC Approval

Regulatory approval gate is cleared.

Hardware Paths
W8

Kit Ready

Existing installation kit modified — 6-week lead only.

W10

OBE Ready

Thales aircraft hardware is ready.

W12

All Aircraft Hardware Ready

Kontron CS/WAP completes the aircraft set.

W18

GN Hardware Ready

Nokia ground hardware — now the critical path.

W13–W15

Logistics & Customs

Shipment, release and transfer to MRO.

W16

Aircraft Installation

One-week installation at the MRO.

W16–W23

Waiting for Ground Network

Installed aircraft waits for ground coverage to go live.

W19–W22

GN Site Installation

Ten ground sites installed in three weeks.

W23

GN Implementation

Ground network integrated with the CORE.

W24

POC Flights

Test flights from Salalah → Muscat or Muscat → Riyadh.

W25

Performance Data

Collect and evaluate in-flight results.

W26

GO Phase

Programme moves into the GO phase and contracts.